Arkhangelsk region administration
Description of work
Delivery, supervising installation and commissioning of a pellet burning boiler house (2 x 0.5 MW) were completed within the shortest possible time. The equipment was delivered in three stages.
First we delivered silos and infeed system, with installation works being started immediately upon delivery. The second stage included delivery of the boiler house and the third – boilers and other equipment delivered at assembling site as transport modules.
Project timeline
Terms for this project realization were rather short. That is why the work was simultaneously organized on three directions – construction, delivery and installation. It took only 5 months from signing the contract on boiler house delivery till start-up (January 2014).