Long-expected modernization of Solombalsky LDK

  • Sorb
  • News
  • Long-expected modernization of Solombalsky LDK
01.06.2012
In the near future a new advanced sawmill will be constructed at the site of Solombalsky LDK, which is to completely replace the old sawmill equipment currently operating there. Designed capacity of the new sawmill will make up some 800 thousand cubic meters of sawlogs processed annually. This project is the next after the one of Lesosibirsky LDK 1 construction, where Hekotek does not only supply its own manufactured equipment, but acts as a project general supplier responsible for complex delivery of equipment for the whole new sawmill. Sorb specialists develop logistics solutions for the equimpment delivery, which is planned for beginning of year 2013 - the new equipment complex will be shipped to Arkhangelsk in February, while the launch of the new the sawmill is to take place by end of Summer 2013.